Friends and family – thank you for being part of this journey! As you know, nothing gets accomplished in life without great people around you.
“You have not lived in the world of competitive sport until …
Do you have the right tools to communicate well in your job?
The purpose of this category is to describe how you can use your Project Management skills to manage social responsibility.
Don’t click here if you like to procrastinate.
Too many methods. Do you know which method is right for your environment?
Tips and general lessons learned for applying professionalism to your environment.
A running list of PM notes I’ve compiled . I found this to be very useful because it puts it in a form to quickly remember the terms. Feel free to add or correct any comments at the bottom and lastly, this is a compiled list of terms that I credit people and sources at the bottom of the list.
Thanks all ..
| 1 | Historical information is the best input for the initiation phase |
| 2 | Operations: are ongoing and repetitive |
| 3 | Getting coffee from Wife is a Project, Getting Coffee from Vending Machine is OPERATION (There are no surprises!..Thanks ARI) |
| 4 | The Resource Breakdown Structure shows various resources, both human and mechanical needed for project. |
| 5 | Acquisition: When the performing organization lacks the in house staff needed to complete the project, the required services can be acquired from outside sources. |
| 6 | Let the people involved in the conflict work it out first |
| 7 | The best use of “collect project records” is to recall what happened on the project, good or bad. |
| 8 | Planning phase is LEAST Risky |
| 9 | Control Management System tracks the changes(not configuration management) |
| 10 | Templates and forms which are available in the organization are reusable components. Any resource that can be reused as a useful tool is part of the total methodology of project planning |
| 11 | Comparing proposals received from sellers done in the Conduct Procurements. |
| 12 | Make payment to seller is done in the Administer Procurements |
| 13 | Engineering is primarily responsible for creating design and test specifications. |
| 14 | Control charts are graphic display of the results over a time of a process. They are used to determine if the process is “in control”. |
| 15 | Pareto chart: Focus on critical issues to improve quality |
| 16 | Fishbone diagram/Ishikawa: Determines how various factors linked to potential problems or effects, root cause |
| 17 | Control chart: Determines whether or not process is stable and within set limits . |
| 18 | Histogram: ordered by frequency of occurrence, that shows how many results were generated by type or category of identified cause. |
| 19 | Planning meetings are used to create the Risk Management plan. |
| 20 | Approximating number of work periods required to complete individual activities with estimated resources is done in Estimate Activity Duration process. Activity List ,Activity resource requirements and Resource Calendars are inputs of Estimate Activity Duration process. PMBOK Page no 177 |
| 21 | Monte Carlo Analysis: A schedule risk assessment technique that performs a project simulation many times in order to calculate a distribution of likely results |
| 22 | The project team, led by the project manager, must write the quality policy for each project. |
| 23 | For an immediate work, a letter contract may be sufficient |
| 24 | Performance Measures are done in contract Administration |
| 25 | Product Verification, Procurement Audit and creation of a contract file are done in CONTRACT CLOSURE |
| 26 | Last step in Administrative closure is Release resources |
| 27 | Employee records should be updated by PM when he completes the tasks assigned to him |
| 28 | Individual development is the Foundation of Team development |
| 29 | T&M – has the characteristics of both Fixed and Cost reimbursement |
| 30 | Procurement Audit is the only tool and Technique of contract closeout process |
| 31 | Procurement Audit is used to identify successes to transfer the success to other procurements |
| 32 | Symbols are always used in the communications |
| 33 | Independent estimates are prepared to compare the cost to an estimate created with |
| 34 | Communication Management plan defines the contents of the performance reports |
| 35 | Team development with WEAK Matrix is very difficult |
| 36 | Product of the Project is Actually created in EXECUTION Phase /Group |
| 37 | Any change in the Project Charter needs to be approved by the SENIOR MANAGEMENT |
| 38 | REFERRENT power= PM’s PERSONALITY POWER |
| 39 | Work Authorization system Ensures that work is done at RIGH T TIME and in proper sequence |
| 40 | Solicitation is the process of obtaining quotations , bids , offer, |
| 41 | The cost expanded at the completion of phase is known as SINK costs |
| 42 | Conflicting priorities in resource assignments – is an issue in the Matrix structure |
| 43 | Monte carlo simulation provides PROBABILITY OF ANY TASK BEING AT THE CRITICAL PATH |
| 44 | Scope verification should be done – WHEN A PROJECT IS TERMINATED to determine the extent of the completion |
| 45 | Jurans Quality Triology = PLANNING IMPROVEMENT CONTROL |
| 46 | UCL : Upper control limit : Is derived from Random variation |
| 47 | UTL : Upper tolerance limit is the higher of two tolerance limits |
| 48 | When original estimates are flawed then EAC = AC + ETC |
| 49 | Functional – FM has more power |
| 50 | Projectized – PM has more power |
| 51 | Balanced – PM and FM has equal power |
| 52 | WEAK – FM has more power |
| 53 | Strong – MATRIX – PM has more power |
| 54 | BUYER provides the SoW |
| 55 | MAKE or BUY is used for PLAN Purchases and Acquisitions |
| 56 | Residual risks are REMINING RISKS |
| 57 | Crashing is applying more resources to shorten the duration |
| 58 | Risk mitigation is to DECREASE THE PROBABILITY OF RISK |
| 59 | ELAPSED TIME is the time inclusive of NON working days |
| 60 | Outsourcing IS RISK TRANSFERENCE |
| 61 | Networks (diagram) identify the Activity dependencies and path convergence risks |
| 62 | If IRR Is given the DO THE PROJECT SELECTION ONLY BASED ON THAT |
| 63 | Sensitivity chart displays sensitivities in DESENDING ORDER |
| 64 | Payment bonds are specifically designed to ensure that the prime contractor provides payment of Subcontractors, laborers, and sellers of material |
| 65 | Quality is the process of completing the scope to meet stated or implied needs. |
| 66 | CRASHING =MORE COST |
| 67 | FAST TRACK =MORE RISK |
| 68 | Monte Carlo analysis gives you:An indication of the risk involved in the project |
| 69 | 85% cost of quality = DEMING |
| 70 | A process goes out of control when there are special causes of variation |
| 71 | Worker needs to be involved in Management Practice = OUCHI’s THEORY Z |
| 72 | Definite cost are most accurate |
| 73 | Sensitivity Analysis are part of Quantitative Analysis |
| 74 | Milestone Duration is ZERO |
| 75 | PERT Is also a NETWORK DIAGRAM |
| 76 | A statistical method that helps identify which factors may influence specific variables of a product or process under development or in production is DESIGN OF EXPERIMENTS |
| 77 | Complex project will best fit in MATRIX org structure |
| 78 | Pert is Superior to CPM |
| 79 | BRUCE TRUKMAN Model is related to TEAMMANAGEMENT |
| 80 | Payback period ended means Cumulative Revenue and cumulative cost from Starnet became equal |
| 81 | Beta Distribution and Triangular distribution are probability distributions used in Risk Analysis |
| 82 | The project management team should have a working knowledge of statistical quality control, especially sampling and probability, to help evaluate quality control outputs. |
| 83 | The area consisting of typically three standard deviations on either side of a mean value of a control chart to plot measured values found in statistical quality control – THIS IS DEFINITION FOR CONTROL CHARTS |
| 84 | large number of simultaneously performed projects utilize the same groups of human and other resources – is called RESOURCE POOLING |
| 85 | The inherent discount rate or investment yield rate produced by the project over a pre-defined period of time. = IRR |
| 86 | PMBOK Guide process groups Interact based on DEMING SHEWARTS PLAN DO CHECK ACT cycle |
| 87 | The critical chain Method modifies the SCHEDULE to account for LIMITED RESOURCES |
| 88 | SCOPE CREEP = UNMANAGED changes to the Project SCOPE |
| 89 | Code of Ethics of PMI = RRFH Responsibility, respect, Fairness, honesty |
| 90 | A group of related scheduled activities – shown as single aggregate activity for the reporting purpose is known as HAMMOCK Activity |
| 91 | Cost base line does not include management reserve |
| 92 | Stake holder model – SALIANCE GRID |
| 93 | As per HERZBERG base Salary is a HYGINE FACTOR |
| 94 | RANK THE IDEAS in BRAINSTOMING – NOMINAL GROUP |
| 95 | Arbitration and mediation are Negotiation Techniques |
| 96 | Standards are OPTIONAL , Regulations are REQUIRED |
| 97 | What is the name and ethical code for adhering PMP = PMI code of ethics and professional conduct |
| 98 | Single source seller means – there is only one seller the company wants to do business with |
| 99 | Cost Performance baseline is represented as S curve |
| 100 | Inspections are NOT called as Assessments |
| 101 | Inspections are called as reviews, Audits and walkthroughs |
| 102 | First time feedback to a team member = Informal verbal (Face 2 Face), second time FORMAL written |
| 103 | Non verbal communication is about 55% |
| 104 | Last stage of project closure is project Archives |
| 105 | CPI is considered most critical EVM Metric |
| 106 | Contract closure occurs before Administrative closure |
| 107 | Resource leveling results in INCREASED PROJECT DURATION |
| 108 | Administrative closure should be carried out at the completion of each phase of the project |
| 109 | Measuring Quality of the product against standard is called Benchmarking |
| 110 | Fait accompli – done deal/ non negotiable |
| 111 | The nodes on the AOA diagrams represent completion of the activities and have ZERO time usage |
| 112 | Straight line depreciation formula= (Initial cost-scrap value)/life |
| 113 | Preparing the Financial plan requires both project Management and Industry specific Skills |
| 114 | Statistical sampling for Inspection is used to reduce the cost of Quality control |
| 115 | One method to determine how well the project is getting executed is using – CPI (Cost performance Index) |
| 116 | Seller completes the work as specified, but the buyer is not happy – then the contract is said to be COMPLETE (not closed though) |
| 117 | TCPI is the projection of the cost performance that must be achieved on the remaining work |
| 118 | The objective of lesions learned document is continuous Improvement |
| 119 | Training for the team members is not a prerequisite – it can happen during the project also |
| 120 | Over allotted – then do resource leveling |
| 121 | Withdrawal – has cooling off period – but the problem is not solved |
| 122 | The most Important criteria for project selection is REALISM |
| 123 | INFLATION – is a EXTERNAL UN Predictable RISK |
| 124 | Team building is difficult in Matrix Org structure |
| 125 | RDU = Remaining Duration |
| 126 | The Pillars of the quality are DOING It RIGHT – first time and ZERO Defects |
| 127 | Project risk is categorized by 3 factors a) Risk event, b) risk probability) amount at stake |
| 128 | Probing, scratching and small bites – are the behaviors of the contract negotiations |
| 129 | The project scope management plan – will not have the project constraints and assumptions (RD, Scope statement and scope BSL – will) |
| 130 | If you have to look/refer any plan – to respond regarding improving customer satisfaction – you need to look at QUALITY PLAN |
| 131 | Lag means – make sure one tasks waits before it gets started |
| 132 | Lead means you let the task get started before its predecessor is done |
| 133 | Output for source selection is contract |
| 134 | Participative leadership is most preferred leadership style |
| 135 | Gert is a System Dynamics model |
| 136 | Trigger is a warning sign |
| 137 | People exhibit slowest rate of change (Bruce willis -16 BLOCKS) |
| 138 | Sponsor does not create project charter |
| 139 | Philip corsby – said QUALITY IS FREE |
| 140 | An Expressed Warranty is a statement of characteristics of the product |
| 141 | Which questions the functional manager is most likely to ask : WHO WILL DO THE TASK |
| 142 | An activity that consumes no time or resources and shows only a dependency = DUMMY Activity |
| 143 | The practice of ceasing mass inspections and ending awards based on price is credited to DEMING |
| 144 | Making a GIANT leap followed by a period of Maturity = INNOVATION |
| 145 | 12 to 20% of the sales is estimated to be the cost of NON QUALITY |
| 146 | To assimilate through the mind or senses is the process of UNDERSTANDING |
| 147 | RISK response of eliminating a threat = RISK AVOIDANCE |
| 148 | The stage of the negotiation meeting – when he points of concession is identified = scratch bargaining |
| 149 | Completion of PROJECT scope is measured against the plan (not PRODUCT SCOPE) |
| 150 | Performance specifications are measureable |
| 151 | Quality control measurements are used to reevaluate and analyze the quality standards and processes and are fed back through: Quality ASSURANCE |
| 152 | The final cost of the project is HIGH at the start and gets progressively LOW as the project continues |
| 153 | On large or mega projects the integration is the responsibility of the project office |
| 154 | If the results fall under customer tolerance then the results are acceptable to client |
| 155 | Benchmarking is a Technique used in QUALITY PLANNING |
| 156 | Lessons learned are professional obligation of the project Manager |
| 157 | The project manager’s ability to influence others whose cooperation and support are crucial to the project is called: DE FACTO AUTHORITY |
| 158 | Taguci loss function states that – VARIATION from Target Value Increases, the Loss also INCREASES |
| 159 | Contract is LEGAL relationship and project is not |
| 160 | Withdrawal is the LEAST preferred method by PM’s |
| 161 | Risk audit documents the effectiveness of the risk responses |
| 162 | Triangular distribution = PERT – Relies on Optimistic, Pessimistic and Most likely estimates(in Risk rating) |
| 163 | Brain storming and Lateral Thinking are used in scope definition for ALTERNATIVES IDENTIFICATION |
| 164 | Progressive Elaboration is what happens in rolling wave planning process |
| 165 | Avoid, Mitigate, Transfer, Accept – are applicable for Negative Risks also |
| 166 | Communications are COMPLEX in Matrix organization |
| 167 | EVM does not play a major role in QUALITY MANAGEMENT PG |
| 168 | Successor Activity LS- Duration of current activity= LS of Current Activity |
| 169 | FIRM FIXED PRICE = Seller carries COST RISK, Buyer carries SCOPE RISK |
| 170 | Releasing the resources from the project is what done as LAST ACTIVITY |
| 171 | Procurement documents ensure the receipt of complete proposals |
| 172 | Project Performance appraisal focus on How individual team member is performing in the team |
| 173 | Baseline is established during the PLANNING |
| 174 | Meetings are always classified as INFORMAL VERBAL |
| 175 | BCR 1.8 means that revenue from the project is 1.8 times the cost |
| 176 | Training the team member in GENERAL Skills is the function of the FUNCTIONAL MANAGER |
| 177 | High Standard Deviation is High Risk. |
| 178 | CPM – FLOAT usage; CCM – Buffer usage. |
| 179 | Costs and staffing levels are lowest early in the life cycle, peak while the project work is underway, and then drop off as the project nears completion. |
| 180 | Risk is highest early in the project since uncertainty is high about the project’s deliverables, resource needs, and work required. |
| 181 | Stakeholder Influence in the project and its deliverables is highest early in the life cycle but diminishes as the project proceeds… |
| 182 | Controlling unexpected project cost is to engage stakeholders early to prevent unnecessary and costly changes later in the project. |
| 183 | The payback period tells us how long it will take to recoup the expense of the project, so a shorter payback period is better. |
| 184 | BALANCED MATRIX: Folks who work in a balanced matrix organization report to a PM AND a functional manager equally. |
| 185 | STRONG MATRIX: Project managers have more authority than functional managers, but the team still reports to both managers. |
| 186 | Portfolio: A portfolio is a group of projects or programs that are linked together by a business goal. |
| 187 | Program: A program is a group of projects that are closely linked, to the point where managing them together provides some benefit |
| 188 | Project: A project is any work that produces a specific result and is temporary. Projects always have a beginning and an end. But they are never ongoing |
| 189 | Portfolios are organized around business goals and Programs are organized around a shared benefit in managing them together.” |
| 190 | ROI = (Benefit – Cost)/Cost |
| 191 | IRR is the discount rate when NPV equals zero. |
| 192 | IRR assumes that cash inflows are reinvested at the IRR value. |
| 193 | IRR: You should choose projects with the highest IRR value. |
| 194 | Mathematical models is that they use linear, dynamic, integer, nonlinear, and/or multi-objective programming in the form of algorithms—or in other words, a specific set of steps to solve a particular problem. Mathematical models are also known as Constrained optimization methods |
| 195 | Benefit Measurement Methods: employ various forms of analysis and comparative approaches to make project decisions. These methods include comparative approaches such as cost-benefit analysis, scoring models, and benefit contribution methods that include various cash flow techniques and economic models. |
| 196 | NET PRESENT VALUE – NPV: When you get a positive value for NPV, it means that the project will earn a return at least equal to or greater than the cost of capital. |
| 197 | INTERNAL RATE OF RETURN – IRR: is the discount rate when the present value of the cash inflows EQUALS the original investment |
| 198 | The primary difference between focus groups and facilitated workshops are that focus groups are gatherings of prequalified subject matter experts and stakeholders and facilitated workshops consist of cross-functional stakeholders who can define cross-functional requirements. |
| 199 | Completion of Project Scope is measured against the Project Management Plan. |
| 200 | Completion of Product scope is measured against Product Requirements. |
| 201 | PMI advocates Project Objectives that follow the SMART guideline. S – Specific; M – Measurable; A – Assignable; R – Realistic; T – Timely. |
| 202 | Control Account may include one or more Work Packages, each Work Package represents only one Control Account. |
| 203 | The WBS doesn’t show the order of the work packages or any dependencies between them. |
| 204 | Scope verification is primarily concerned with ACCEPTANCE of deliverables. Quality control is done before scope verification. |
| 205 | Product scope: means the features and functions of the product or service that you and your team are building. |
| 206 | Project scope: is all of the work that needs to be done to make the product. |
| 207 | The work package is the LOWEST level on a WBS; |
| 208 | The WBS doesn’t show the order of the work packages or any dependencies between them |
| 209 | Verify Scope: The process of formalizing acceptance of the completed project deliverables. Usually performed after Perform Quality Control. |
| 210 | Verify Scope happens at the end of each phase and the project and upon delivery of Product/Service/Result. |
| 211 | Verify Scope is concerned with completeness and acceptance, and Perform Quality Control is concerned with correctness. |
| 212 | If the project is cancelled/terminated before completion, Verify Scope is performed to show where the Project was in relation to the Scope when it ended. |
| 213 | If we don’t receive a final sign off from our customer; we have to escalate the issue to our Management. |
| 214 | Defining activities is an iterative process performed together by the project manager and the project team member by further decomposing the WBS work packages |
| 215 | ADM’s drawback is that it can only show finish-to-start (FS) relationships |
| 216 | In order to show relationships between tasks on different node branches, ADM diagrams use dummy activities |
| 217 | The Arrow Diagramming Method (ADM) creates diagrams known as activity-on-arrow (AOA). |
| 218 | The Precedence Diagramming Method (PDM) creates diagrams known as activity-on-node (AON). |
| 219 | Lead time causes the successor task to begin before its predecessor task concludes…for example FS-2 would schedule the successor task to start before the predecessor task finish. |
| 220 | Lag time causes the successor task to begin some time after its predecessor task concludes…for example, FS+1 would delay the start of the successor by 1 day. |
| 221 | Rough order of Estimate = +-50% |
| 222 | Resource Calendars specify WHEN and HOW LONG identified project resource will be available during the project. |
| 223 | Analogous is TOP DOWN |
| 224 | Parametric is More Accurate |
| 225 | Bottoms up is Accurate (When Parametric was not given) |
| 226 | Duration is the amount of time that an activity takes, while effort is the total number of person-hours that are expended. |
| 227 | Resource leveling can cause the original critical path to change. |
| 228 | Path Convergence: The merging or joining parallel schedule network paths into the same node in a project schedule network diagram. |
| 229 | Path convergence is characterized by a schedule activity with more than one predecessor activity. |
| 230 | Path Divergence: Extending or generating parallel schedule network paths from the same node in a project schedule network diagram. |
| 231 | Path divergence is characterized by a schedule activity with more than one successor activity. |
| 232 | Sunk Costs: costs incurred that cannot be reversed irrespective to future events |
| 233 | Value Engineering/ Analysis: finding less costly way to do the same work. E.g. outsourcing |
| 234 | Marginal analysis: Spend time on improvement if it improves revenues or productivity. |
| 235 | Order of Magnitude Estimate: Rough Order of Magnitude (ROM): -50% to +50% (at Initiation) as the project moves, estimates should become more accurate, |
| 236 | Direct cost: include dedicated labor, material, supplies, equipment, licenses, fees, training, travel, or professional service fees – [Applied directly to THIS project] |
| 237 | Indirect cost: Example, if a color printer is shared by several project teams, it’s difficult to definitively determine what percentage of costs each should share. [Expenses not for ONE project - these are Shared Expenses] |
| 238 | Variable cost: fluctuate and can’t be predicted with absolute certainty. For example, travel or transportation costs that can change depending upon the cost of fuel or certain commodities and types of raw materials. |
| 239 | Fixed cost: are static throughout the project or have only a small likelihood of fluctuation. Fixed costs are usually for items such as rents, leases, licenses, salaries, and fixed fees |
| 240 | Life Cycle Costing includes Acquisition, Operation, Maintenance, and Disposal Costs |
| 241 | The Scope Statement provides the Product Description, Acceptance Criteria, Key Deliverables, Project Boundaries, Assumptions, and Constraints about the Project. |
| 242 | QUALITY: is defined as degree to which your project fulfills requirements. Customer satisfaction, Fitness for use, Conformance to requirements |
| 243 | Cost benefit: Looking at how much your quality activities will cost. |
| 244 | Benchmarking: means using the results of quality planning on other projects to set goals for your own. |
| 245 | Design of experiments: is the list of all the kinds of tests you are going to run on your product. |
| 246 | Attribute Sampling: is binary, it either conforms to quality or it doesn’t (YES or NO). |
| 247 | Variable Sampling: Measures how well something conforms to quality (RANGES). |
| 248 | Special Causes: considered unusual and preventable by process improvement. |
| 249 | Common Causes are generally acceptable. |
| 250 | Tolerances deal with the limits your project has set for product acceptance. |
| 251 | Control Limits are set at three standard deviations above and below the mean. As long as your results fall within the control limits, your process is considered to be in control. |
| 252 | Tolerances focus on whether the product is acceptable, while Control Limits focus on whether the process itself is acceptable. (Control limit is for PROCESS) |
| 253 | Control Charts: The upper and lower control limits are set at THREE STANDARD DEVIATIONS ABOVE and BELOW MEAN. |
| 254 | Rule of Seven: If seven or more consecutive data points fall on one side of the mean, they should be investigated. This is true even if the seven data points are within control limits. |
| 255 | Just In Time (JIT): To reduce expensive cost of holding inventory, many companies decrease inventory close to zero. A company using JIT must have high quality practices. |
| 256 | Cost of Quality = Prevention cost + Appraisal cost + control cost |
| 257 | Low grade is OK, but Low Quality is NOT OK |
| 258 | Quality assurance is focused on the processes and not the quality of the deliverables. |
| 259 | This is important for us to remember: quality assurance is concerned with quality processes while quality control is concerned with quality deliverables. |
| 260 | Flow Chart: Shows HOW PROCESSES INTERRELATE. |
| 261 | Histogram (Column Chart): It shows HOW OFTEN something occurs, or its FREQUENCY (no Ranking). |
| 262 | Pareto Charts (80-20 rule): This is a Histogram showing defects RANKED from GREATEST to LEAST. This rule states that 80% of the problems come from 20% of the causes. It is used to help determine the FEW ROOT CAUSES behind the MAJORITY OF THE PROBLEMS on a project. |
| 263 | Run Chart: tell about TRENDS in the project. Shows the HISTORY and PATTERN. |
| 264 | Scatter Diagram: It is powerful tool for SPOTTING TRENDS in Data. Scatter Diagrams are made using two variables (a dependent variable and an independent variable). |
| 265 | W. Edwards Deming = Plan DO- check- Act + He also developed 14 activities for implementing quality |
| 266 | Philip Crosby = ZEro Defects, |
| 267 | Dr. Genichi Taguchi developed the concept of ‘Loss Function’. |
| 268 | KAIZEN = process Improvement |
| 269 | special causes are considered preventable. For example, a backup generator failed to start up during a power failure. The failure of the backup generator can be prevented in the future through regular mechanical maintenance and operational tests. |
| 270 | Common causes are thus generally considered as non-preventable and accepted as part of the process. |
| 271 | Inspection keeps errors in the product from reaching the customer. Prevention keeps errors from occurring in the process. |
| 272 | FORMAL, REWARD, PENALTY are powers derived from project managers position in the company. |
| 273 | Theory X – Autoritarion leadership style |
| 274 | Theory Y – Autoritarion Democratic/ Laissez- faire leadership style |
| 275 | Theory Z – Autoritarion Democratic leadership style |
| 276 | Laissez-faire: The leader turns nearly all control over to the group and is generally absent. |
| 277 | In a matrixed organization, the project manager doesn’t have legitimate power, because the team doesn’t directly report to the project manager. |
| 278 | Conflict can come from seven main sources, of which the first three account for 50% . They are 1. Schedules, 2. Priorities, 3. Manpower/human resource availability, 4. Technical opinions, 5. Procedural or project administration, 6. Costs,7. Personalities (SP is first 2 and CP is last 2) |
| 279 | Generally, only one person is assigned Accountability for a work package, but more than one person may be responsible for performing the work on a work package |
| 280 | Confronting: It’s a Win-Win situation |
| 281 | Compromising: Lose-Lose method |
| 282 | Withdrawal: Lose-Leave method |
| 283 | Smoothing: Lose-Yield method |
| 284 | Forcing: Win-Lose method (Worst way). |
| 285 | Salience Model – describing classes of stakeholders based on their Power, Urgency and Legitimacy. |
| 286 | SENDER’S responsibility to make the message clear, complete, and understood |
| 287 | Nonverbal communication means your gestures, facial expressions, and physical appearance while you are communicating your message. |
| 288 | Paralingual communication is the tone and pitch of your voice when you’re talking to people. If you sound anxious or upset, that will have an impact on the way people take the news you are giving |
| 289 | Distribute Information is concerned with general project information, such as meeting minutes, issues, and correspondence. |
| 290 | Report Performance focuses on performance reporting against baselines, such as scope, schedule, cost, or quality. Report Performance uses time, cost, and related work performance information. |
| 291 | According to Kerzner – “90% of the Project Manager’s time is spent communicating” |
| 292 | Management Skills = Presentations skills, negotiation skills, writing and public speaking skills. |
| 293 | Risk Breakdown Structure (RBS): It is not breaking down the actial risks, instead, we are breaking down the CATEGORIES of risks that we will evaluate. |
| 294 | The amount of tolerance a person or organization has for risks is referred to as its risk utility, |
| 295 | Watchlist: Low priority risks should be regularly monitored so make sure they are not occurring and that their probability, impact, or priority hasn’t changed. |
| 296 | Risk Score: The probability and impact score for the risk. This is obtained from a formula (usually probability x impact) defined in the risk management plan and generated from the probability and impact matrix. |
| 297 | The management reserve is for unknown-unknowns—things that you haven’t planned for but could impact your project. |
| 298 | The contingency reserve is for known – unknowns, or risks that you know about and explicitly planned for and put in your risk register. |
| 299 | Transfer: Transference assigns all or part of risk to a third party through outsourcing, contracts, insurance, warranties, guarantees, or performance clauses. |
| 300 | Risk response- fails> then contingency plan…If contingency plan fails then > Fall back plan, i.e in other words=> It can be looked at as a contingency plan for the contingency plan |
| 301 | CPFF – More risk for BUYER (some say T&M) |
| 302 | FFP – More risk for SELLER |
| 303 | UNILATERAL: this is a special class of contract in which the seller doesn’t have to explicitly accept the offer in order for a contract to be established. This is a unilateral contract, and the best example is a purchase order (PO). |
| 304 | Procurement closure needs to happen before Project Closure. All procurements MUST be CLOSED before the project is closed. |
| 305 | Administrative closure is COMPLETE PROJECT Closure – so it can be done only once for project (or) Phase |
| 306 | Claims are usually addressed through the contract change control system |
| 307 | The payment system is how your company pays its sellers. |
| 308 | 100% rule comes in WBS |
| 309 | Force Majeure Risks, such as Earthquakes, Floods, Acts of Terrorism, Etc., should be covered under Disaster Recovery Procedures instead of Risk Management. |
| 310 | Journey to Abilene= Committee decisions can have the paradox outcome, that a jointly made or approved decision is not desired by any individual group member.(nobody likes the outcome) |
| 311 | What is a constructive change? = consideration of undocumented change = A direction by the buyer or an action taken by the seller that the other party considers an undocumented change to the contract. |
| 312 | Getting collective action from a group of people who may have quite different interests is ‘Politics’. |
| 313 | Arbitration is a form of negotiation. Technically, it is a form of assisted negotiation. |
| 314 | Primary Responsibility of the Project Manager is ‘Interact with others in a Professional Manner while completing the project’. |
| 315 | GERT, Graphical Evaluation and Review Technique, allows for conditional advancement. GERT allows for branching and loopbacks. |
| 316 | Subnets are often included in network templates to summarize common activities in a project. |
| 317 | Parkinson’s Law states that work will expand to fulfill the time allotted to it. (SUPER!- That’s what we do in real life right…) |
| 318 | Soft logic allows the project manager to make decisions based on conditions outside of the project, best practices, or guidelines. |
| 319 | Milestone Schedule can also be called as Master Schedule. |
| 320 | The arrow diagramming method does not support finish-to-finish of relationships. |
| 321 | GERT is the only diagramming technique that allows loops. |
| 322 | The primary purpose of a network diagram is to show logical relationships. |
| 323 | Value analysis is a way of finding the least expensive way to do the work. |
| 324 | Fringe benefits are included in overhead and are part of indirect costs. |
| 325 | QA is typically management process |
| 326 | Q: Optimal quality is reached at what point? A: When revenue from improvement equals the incremental costs to achieve the quality. Marginal analysis provides that optimal quality is reached when the cost of the improvements equals the incremental costs to achieve the quality. |
| 327 | Design of experiments uses experiments and ‘what-if’ scenarios to determine what variables are affecting quality. |
| 328 | Having an allowable defect rate is an example of the cost of non-quality. Any system or process that will accept defects adds cost to the product or service. |
| 329 | Staffing Management Plan: WHEN and HOW resource will be ADDED and TAKEN OFF the team. |
| 330 | A corner office is a “perk” whereas health benefits are a fringe benefit. |
| 331 | Mentoring: is the work that a project manager may be frequently called on to perform. |
| 332 | Performance issues are senior and functional management’s responsibility – usually the manager who supervises the resource. |
| 333 | Conflict is not a filter of communication—it is a communication hindrance. |
| 334 | Nonverbal communication carries 55 percent of the message you send. With this much at stake, nonverbal communication is of major importance. |
| 335 | The utility function describes a person’s willingness to tolerate risk. |
| 336 | For immediate work, a letter contract may suffice. The intent of the letter contract is to allow the vendor to get to work immediately to solve the project problem. |
| 337 | When you must begin work immediately without a procurement statement of work, the most appropriate choice is time and material. |
| 338 | Outputs of all 42 Processes will be stored in PMIS. |
| 339 | Cause & Effect/Ishikawa/Fishbone Diagram or 5 WHY Technique. |
| 340 | The BIG Four: 1. Ishikawa; 2. Deming; 3. Juran; and 4. Crosby. |
| 341 | Leads and lags are APPLIED as part of the Develop Schedule process, but then they are ADJUSTED in the process of Control Schedule. |
| 342 | Zero Schedule Varience (SV) means the task is completed. |
| 343 | The To-Complete-Performance-Index (TCPI) is: The cost performance index (CPI) required in the remainder of a project to meet financial goals. |
| 344 | The S curve is the cost performance baseline. The cost performance baseline is used to track cost performance based on the original plan plus approved changes. |
| 345 | Requirement Traceability Matrix helps preventing gold plating |
| 346 | Parametric Estimates may not scale |
| 347 | For cost plus contract RFP is suitable |
| 348 | NPV will help u to build most precise business case |
| 349 | Standard deviation in a chart measures PRECISION |
| 350 | Changing Management Approach based on the team members experience = SITUATIONAL CONTINUUM |
| 351 | PMIS resides in EEF (enterprise environmental factors) |
| 352 | ARMA is a econometric method (Auto regressive moving average) |
| 353 | LOI is not a legal document |
| 354 | PM can not be a lead negotiator |
| 355 | Work Authorization systems helps in preventing scope creep |
| 356 | Outputs of Project Management info system are deliverable(s) |
| 357 | 3 causes of team conflict are: Schedule, Priority, Costs |
| 358 | Negotian is working with Others Arbitration/Mediation |
| 359 | Integrate Change Control DNA are ensures changes are agreed upon, changes have/has occurred, manage Change. |
| 360 | Risk are in the FUTURE; Issues are present |
| 361 | Project Risk has its origins in the uncertainty present in all projects. |
| 362 | unknown risks cannot be managed proactively, which suggests that the project team should create a contingency plan |
| 363 | Risk attidues are driven by perception, tolerances, and other biases |
| 364 | A workaround is a response to a negative risk that has occurred. It differs from a contingency plan in that a workaround is not planned in advance of the occurrence of the risk event |
| 365 | Having a contract change control system will allow you to establish the procedures and process should you need to modify a contrac |
| 366 | Phase exits, Phase gates and Kill points refer to the same term and refer to a phase end review with the objective of obtaining authorization to close the current phase and begin on the next one. When phases are sequential, the close of the a phase ends with a some form of transfer or handoff of the work product procedurd as the phase deliverable. |
| 368 | Create WBS process identifies the deliverables at the lowest level in the Work Breakdown Structure |
| 369 | Deming 80% of the problems is |
| 370 | Process Improvement models include: Malcom Baldrige, Organization Project Management Maturity Model (OPM3) and Capability Maturity Model Integrated (CMMI) |
| 371 | Cost of Qaulity (COQ) refers to the total cost of all efforts related to quality throughout the product life cycle. |
| 372 | Parento roughly 80% of the effects come from 20% of the causes. |
| 373 | Finish-To-Start. The initiation of the successor activity depends upon the completion of the predessor activity |
| 374 | TQM and Six Sigma are quality improvements |
| 375 | Finish-to-Finish: The completion of the successor activity depends upon the completion of the predecessor activity |
| 376 | Start-to-Start (ss). The initiation of the successor activity depends upon the initiation of the predecessor activity |
| 377 | Start-to-Finish (SF) The completion of the successor activity depends on the the initiation of the precessor activity (least used) |
| 378 | Work Authorization is a permission and direction to begin work on a specific Schedule activity, Work Package, Control Account |
| 379 | Anything that interferes with the transmission and understanding of a message is termed noise. Distance would be such an example, as in the case of global teams. |
| 380 | A preimposed deadline or milestone is an example of a constraint |
| 381 | Constraints limit the flexibility in the HR planning process. Examples are: 1) Organizations whose basic structure is a weak matrix means a relatively weaker role for a project manager. 2) Collective bargaining agreements – contractual agreements with unions or other employee groups can require certain roles or reporting relationships. [Project Human Resource Management] |
| 382 | |
| 383 | |
| 384 | |
| 385 | |
| 386 | |
| 387 | |
| 388 | |
| 389 | |
| 390 | |
| 391 | |
| 392 | |
| 393 | |
| 394 | |
| 395 | |
| 396 | |
| 397 | |
| 398 | |
| 399 | |
| 400 |
This is compiled listing from various source and I got this idea from Raga’s 355 Point (http://pmzilla.com/raga039s-355-points). PMBOK4, Rita, PMZILLA.COM,
As I have mentioned in the past, any commitment to either losing weight or endurance training lifestyle doesn’t have to an “off season”. Making a commitment for your life style is a choice but as …
Hi there!
I have been enjoying Google Insight Tool for researching new trends using keywords. For all of you who would like to research and you want get organic search from internet and monetize your blog with high traffic, this is a …
[image] Dare to try it?Dare to try it?
Hi everyone!
Wow, what can I say about you and your support for this years fund raising efforts for the MS Society. Because of your contributions, you have made a person with MS life a little …
Does completing a goal mean anything to you? It did for Sian Welch & Wendy Ingramham..
Sian Welch & Wendy Ingraham – The Crawl – 1997.
My question to you is, what makes you finish?
Below is the track log for the Surf City 1/2 Marathon event February 1st. If you dare to do it and be committed, we’ll help you reach your goal!
During the week, you can train and …
THANK YOU!!…This note is way over due and I apologize for not sending a thank you note last month for your kind contribution and/or support for the fund raising we took on this year.
Over the …
This section is still in progress, however, I found some pretty good stuff from Dr. David Hartl
USE DIFFERENT COMMUNICATION STRATEGIES FOR DIFFERENT PEOPLE AND DIFFERENT SITUATIONS.
Help people get what they need to know in ways that suit …
Just when you thought you could stop getting another certificate, the Project Management Institute is pushing more than ever that PMs should should get certified. Especially now and before the PMBOK 4th addition comes out …
Are Business System Analyst salaries going down?
Not really, according to salary.com, starting salary for BSAs start at $55,000 per year. Add the goodies and you could be making as much as $80,000 a year (See …